STP 2940(1) [VT Route 30 Reclamation Project]
DATE: Friday, July 14, 2023
TRAFFIC IMPACT AND DURATION: Monday, July 17, through Friday, July 21, from 7:00 a.m. to 7:00 p.m., motorists can expect two traffic control packages with alternating one-way traffic on Vermont Route 30 (VT 30) throughout the project limits.
Delays are expected. Motorists are advised to add extra time to their travel schedule.
Speed limits have been reduced to 40 mph throughout the project limits. Fines are doubled for speeding within the construction zone. Motorists are advised to follow the posted speed limit and travel with caution as there are various roadway surfaces throughout the project limits, including gravel roadway.
Motorists should anticipate adverse road conditions during and after rainfall and should also expect the presence of grading equipment on the road following storm events.
CONSTRUCTION ACTIVITIES: Crews will continue fine grading beginning near the covered bridge in Dummerston and moving north towards Newfane. Crews will continue paving the intermediate course of pavement in Brattleboro moving north. All work is weather dependent.
PROJECTED COMPLETION: Fall 2023
New Contact Information for the Brattleboro-Newfane VT Route 30 Reclamation Project
The Brattleboro-Newfane Roadway Reclamation Project along VT Route 30 between Brattleboro and Newfane has updated its contact information for the public seeking project information. As of June 26, 2023, a new project email address and hotline phone number have been established to assist the public. For any project questions, comments or concerns, please reach out to the Public Information Team using the contact information below.
Brattleboro-Newfane Public Information Team
Hotline: 802-496-9927
Email: info@BrattleboroNewfaneVT30.com
What is a Reclamation Project?
Use the linkbelow to view the flyer for answers to some facts and questions on the roadway reclaim process as well as some general schedule information for operations throughout the summer and fall.
PROJECTED COMPLETION: Fall 2023